Mongolia pushes to complete rail bypass around Ulaanbaatar
A freight train winds its way between between Tynh and Narst in Mongolia. The new railway will branch from the Trans-Mongolian railway southeast of Ulaanbaatar. / Kabelleger / David Gubler, cc-by-sa 4.0
By Michael KohnAugust 18, 2026
Mongolia is making rapid progress on a new 127-kilometre (79-mile) railway that will allow cargo and hazardous products to bypass Ulaanbaatar, a long-awaited project that could significantly impact the way freight flows around the fast-growing capital city.
The Bagakhangai–Khushig Valley–Emeelt railway will branch from the existing Trans-Mongolian railway at Bagakhangai Station, southeast of Ulaanbaatar, run through Khushig Valley and reconnect with the main line at Emeelt Station west of the capital.
The Mongolian tughrik (MNT) 1.2-trillion ($333.6m) project is being built by state-owned Mongolian Railway (MTZ) and includes four railway stations and three passing sidings along the route.
The Bagakhangai–Khushig Valley–Emeelt railway is long-awaited.
Construction began in April 2025 on the 87.8-km Bagakhangai–Khushig Valley section. According to the government, the main construction on that section is now complete. Work on the Khushig Valley–Emeelt section began this year.
The government has ordered officials to have the railway ready for test runs in September. Full operation of the route could occur as early as December.
The railway is being built primarily to move dangerous freight away from populated areas of Ulaanbaatar. Once completed, it will carry gasoline and other petroleum products, as well as explosives and chemically hazardous cargo and coal destined for power plants.
"This dangerous cargo will be transported via the Bagakhangai–Khushigiin Valley–Emeelt direction, not through Ulaanbaatar city," Prime Minister Uchral Nyam-Osor told reporters during a visit to the project site on August 13.
The need to remove hazardous freight from the capital gained added urgency after a deadly accident in January 2024, when a heavy transport truck carrying liquefied gas collided with a vehicle in Ulaanbaatar and exploded, killing six people and igniting a large fire (See archived news video report at foot of this article)
In addition to the safety aspect, moving cargo trains around the city is also expected to reduce wait times at railway crossings. The government adds that train use could also take hundreds of trucks off Ulaanbaatar’s roads.
The new line is being constructed on a considerably more direct alignment than the older railway that goes past Nalaikh and through Ulaanbaatar.
"The old line was built like a snake. Now, the route is direct," said Uchral.
One of the project's largest structures is a new railway bridge over the Tuul River. The government says the bridge will be 476 metres long, making it the longest railway bridge in Mongolia.
Mongolian Railway officials said engineers are working to protect the flow of the Tuul River during construction.
The government says a total of 95 Mongolian companies and more than 4,000 Mongolian engineers and workers are participating in the railway project.
Uchral emphasised the domestic nature of the construction, saying Mongolians had reached a point where they could undertake major railway projects themselves.
The railway is also intended to play a much broader role in the development of the Khushig Valley, home to Chinggis Khaan International Airport, completed in 2021.
With around 1.7mn people now living in Ulaanbaatar, the population has doubled over the past two decades, and the government is looking to take pressure off the capital’s infrastructure by encouraging its residents to move to satellite towns.
The government envisions the Khushig Valley as playing a key role in that effort and is promoting it as a major transportation and logistics hub rather than simply an airport district. A new logistics centre is planned there, with the railway providing a connection that could allow some freight and logistics operations to move out of Ulaanbaatar.
Russia has begun its campaign against Ukraine's energy system weeks earlier than in either of the past two winters, and this time the aim is to stop the repairs before they finish.
Russia's main state development bank has sacked its chief economist over a speech he gave three months ago, in which he said the Russian economy would survive.
Serbia's banks booked record profit of €1.4bn in 2025 and their fastest credit growth in a decade, even as home-grown AIK Banka buys up rivals across the Balkans.
Any attempt to reject the 97.7% vote risks dismantling twenty-five years of delicate peacebuilding, making the August 27 session one of the most consequential moments in modern Pacific history.
This site uses cookies - small text files that are placed on your machine to help the site provide a better user experience. In general, cookies are used to retain user preferences, store information for things like shopping carts, and provide anonymised tracking data to third party applications like Google Analytics.
As a rule, cookies will make your browsing experience better. However, you may prefer to disable cookies on this site and on others. The most effective way to do this is to disable cookies in your browser. We suggest consulting the Help section of your browser or taking a look at the About Cookies website which offers guidance for all modern browsers.
We use cookies to ensure that we give you the best
experience on our website. If you continue we'll assume
that you are happy to receive all cookies from this
website.
AcceptView Cookie
Policy
Please complete your registration by confirming your
email address.
A confirmation email has been sent to the email
address you provided.
Recover password
A confirmation email has been sent to the email
address you provided.
Recovery token has
expired or doesn't exist.
Access recovery request has expired, or you are using
the wrong recovery token. Please, try again.
Complete registration
process
To continue viewing our content you need to complete
the registration process.
Please look for an email that was sent to
with the subject line
"Confirmation bne IntelliNews access". This email will have
instructions on how to complete registration
process. Please check in your "Junk" folder in
case this communication was misdirected in your
email system.